LRCA has regularly sought improved communication from Rotorua Lakes Council regarding the sewerage scheme at East Rotoiti.
On 8 October LRCA received confirmation from Infrastructure Management that the tender invitations for the onsite pretreatment sewerage systems were sent to the 6 shortlisted main contractors the previous week, with the deadline in mid November.
They predict that the evaluation team will have reviewed tenders before Christmas. They plan to conduct community consultation about the preferred option in January during the holiday period.
They have agreed to work with Phill Thomas (Lake Community Board) and LRCA in regards to planning the Community Consultation.
At the conclusion of consultation, management will submit their recommendation to councillors for the pretreatment sewerage system to be installed on east Rotoiti properties.