East Rotoiti Sewerage Scheme Update

5 April 22

East Rotoiti Sewerage Scheme Update

Gerhard Mostert, of RLC advises that progress is tracking well with 24 Biolytix installations complete and 40 properties booked for installation.

Fulton Hogan advise that with the great spell of dry summer weather experienced over the previous 3 months, the focus has continued to be around properties where high ground water level is a challenge. As winter conditions approach, we intend to move away from these low lying areas and focus on “drier” sites. Due to an increase in bookings, Fulton Hogan will begin to bring in additional resources to assist with the programme delivery.

Read the full Rotorua Lakes Council report here including updates from the Ngati Pikiao Cultural Impacts Team, Fulton Hogan and before and after photos showing the tidy final result.